TCU Montgomery RENOVATION
The exterior secured entry/office for early learning area construction has begun. You can see the secured entry office area windows on the left hand side and future main entry/vestibule area on the right hand side. Last weekend’s crane lift of roofing materials onto the building went well. Face brick on the secure entry has begun. Internal demolition will start right away on Thursday, May 23. For those who are not familiar with this area, it is on the east side of TCU Montgomery near the gym parking lot.
Timeline:
Timeline:
- April/May staging area - northeast corner parking lot
- April/May renovation area exterior lintel work
- Summer staging area - entire parking lot
- Renovation area cleared & ready May 23